RCR Power Projects
Structural, Mechanical, Piping & Electrical (SMPE)
RCR Power/RCR Resources
|
Client: |
Fortescue Metals Group |
|
Location: |
Solomon Mine, Pilbara WA |
|
Duration: |
Nov 2011 - Ongoing |
|
|
|
RCR has been contracted to carry out Engineering, Procurement & Construction works (EPC) and pre-commissioning of Fortescue's King's Ore and Firetail Ore Processing Facilities at the Solomon Mine.
The scope includes RCR core competencies of Structural, Mechanical, Piping and Electrical (SMPE) works and is scheduled for completion in December 2012.
The contract is valued at over $600 million, and follows receipt of equipment orders for apron feeders and belt feeders to RCR's Mining Business by Fortescue for the Solomon project totalling $30 million.
Electrical and Mechanical Construction
RCR Power
|
Client: |
IHI Engineering |
|
Location: |
Yurralyi Maya Power Station, Karratha, Western Australia |
|
Duration |
2009-2010 |
RCR provided construction, testing and commissioning services for four new gas turbines at the Yurralyi Maya Power Station site near Karratha, Western Australia.
The scope of services included the provision of electrical and mechanical services, engineering services, procurement of materials and equipment, and testing and commissioning services for the power station’s construction.
Electrical Instrumentation
RCR Power
|
Client: |
Oz Minerals |
|
Location: |
Prominent Hill, South Australia |
|
Duration |
2009 |
RCR managed a workforce in excess of 200 employees on the electrical, pneumatic, instrumentation, control and structural elements for the production of the concentrate from primary crushing through process to storage. During more than 200,000 man hours, RCR installed:
- More than 230km of cable
- 15km of cable ladder
- 12km of conduit
- Five switch rooms, two of which were over 140 metres long
- Pneumatic air control for flotation and frother areas
- Quality control and quantity surveying
Structural, Mechanical, Piping and Electrical Construction
RCR Power and RCR Resources
|
Client: |
BHP Billiton |
|
Location: |
Cliffs Nickel, Western Australia |
|
Duration |
February 2008 – September 2008 |
Together with RCR Resources, RCR Power supplied structural, mechanical, piping and electrical construction services. RCR’s SMPE works included:
- All mining surface infrastructure
- Construction and installation of paste plant
- Electrical site services
- 100V reticulation
- Manufacture, supply and install of four
- 1000/415 volt skid-mounted substations
- SB01, SB02 33,000 volt and 11,000 volt high voltage substations
- Communication works